Finished goods came off a work order and costing must put a price on them, before the work order closes, that price comes from the “provisional completions” setting on the cost profile. If it says “at standard cost”, a published standard must exist for that date. If it says “at average”, the finished item needs an average from somewhere, a previous WIP close, a PO receipt, a costed misc receipt. Neither exists, so the completion waits unpriced.
Provisional-completion setup points at a cost (standard or average) that doesn't exist yet.
My Oracle Support document IDs for readers with access: 2245288.1. We do not reproduce their content.
Checked Cost Management troubleshooting for Oracle Fusion, rewritten in plain words from publicly known practice and reviewed by a working consultant. Checked against the current release, Jul 2026. Navigation and behavior vary by configuration; verify in your own instance and test before acting.